Please use this identifier to cite or link to this item: https://repositori.uma.ac.id/handle/123456789/20817
Full metadata record
DC FieldValueLanguage
dc.contributor.advisorSingh, Raspal-
dc.contributor.advisorBanjarnahor, M.-
dc.contributor.authorB., Iskandar Zulkarnain-
dc.date.accessioned2023-08-25T03:05:44Z-
dc.date.available2023-08-25T03:05:44Z-
dc.date.issued2006-09-
dc.identifier.urihttps://repositori.uma.ac.id/handle/123456789/20817-
dc.description58 Halamanen_US
dc.description.abstractPT Perusahaan Gas Negara ( Persero ) Tbk. merupakan suatu perusahaan pelayanan masyarakat yang sudah Go Public, yang salah satu tujuannya adalah untuk meningkatkan taraf hidup masyarakat. Keterbatasan supply BBM, harga yang semakin tinggi serta biaya yang sangat besar apabila perusahaan melakukan overhaul pada mesin industri, membuat PT Perusahaan Gas Negara ( Persero ) Tbk. berupaya semaksimal mungkin untuk mencari solusi pengganti BBM. Karena keterbatasan supply BBM tersebut, maka banyak industri maupun masyarakat yang mengajukan permohonan agar kiranya dapat menjadi konsumen ( Pelanggan) gas bumi di PT Perusahaan Gas Negara ( Persero) Tbk. Hal tersebut diatas membuat adanya peningkatan jumlah konsumen terhadap kebutuhan gas bumi sebagai alternatif pengganti bahan bakar, oleh karena itu PT Perusahaan Gas Negara ( Persero ) Tbk berupaya seoptimal mungkin dalam menganalisa sistem perencanaan ekspansi ( pengembangan ) jaringan distribusi gas yang dimilikinya. Menyadari betapa pentingnya hal tersebut, maka diperlukan suatu pembahasan atau penelitian langkah-langkah apa yang harus diambil oleh PT Perusahaan Gas Negara ( Persero ) Tbk. Pemilihan judul ini berdasarkan atas masalah yang dihadapai oleh perusahaan dalam proses pemasangan pipa distribusi gas bumi dalam hat ini adalah proses perencanaan, yang mana dalam didalam perencanaan ini masih belum menggunakan metode analisa jaringan sebagai alat pengendalian pelaksanaan proyek. Atas dasar hal tersebut maka penulis mencoba membuat suatu metode analisa jaringan pada proyek pemasangan pipa distribusi gas bumi dengan menggunakan metode PERT ( Programming Evaluation and Review Technique) Penulis mengambil sampel pada proyek pemasangan pipa distribusi gas bumi di PT Universal Gloves Industri, kerja sama antara PT Perusahaan Gas Negara ( Persero ) Tbk SBU Distribusi Wilayah III Sumbagut Distrik Medan dengan PT. Agnes Jaya selaku kontraktor pada proyek tersebut. Dari hasil analisis yang dilakukan dengan metode PERT di peroleh total waktu prnyelesaian proyek adalah : 57.35 hari dengan Standart deviasi = I 0.33. maka probabilitas penyelesaian proyek P = 0,59 atau 59 %. PT. Gas of State Company ( Persero) Tbk. Regional II I Sumbagut, Medan District represent of siciety service company which have Go Public, which one of the target is to improve live level society. Limitation of fuel supply, exelsior price and also big expensive if company conduct overhoul with indu strial machine,making PT. Gas of State Company ( Persero ) Tbk, should be coping as maximum to looking for subtitution of fuel solution. To make realizing the mentioned, so many society and indu stry which apply to be presumably can become consumer ( patient ) in PT. Gas of State Company ( Persero ) Tbk. With existence to improvement amount of consumer to requirement of eart gas subtitution of fuel alternatif, so PT. Gas of State Company ( Persero ) Tbk, should be to maturedly analyse planning system ( development ) of gas owned distribution network. Because an importan to realizing them, so we needed to get solution research of stage, steps what have to be taken by PT. Gas of State Company ( Persero ) Tbk. Election of this title by vertue of problem which it get by company with of instalation of earth gas distribution pipe in this case process planning, which in the plan still not yet used method analysis network as a means of operation on project execution, because the mentioned of the basis so the writer to make try a analyse network method with installation of earth gas distribution pipe project by using PERT method (Programming Evaluation And Review Technique ). The writer get a sample with distribution of earth gas pipe I ine in stallation project in PT. Universal Gloves Industri, activity between PT. Gas of State Company ( Persero) Tbk with PT. Agnes Jaya. From result of conducted with PERT method (Programming Eva luation And Review Technique ), that known the totalizing time of solving project is : 57,35 days ~ 57 days, with deviasi standart = 10,33 . and Z = 60 days, so the project probability can finish is P = 0,59 or 59%.en_US
dc.language.isoiden_US
dc.publisherUniversitas Medan Areaen_US
dc.relation.ispartofseriesNPM;018150004-
dc.subjectperhitungan waktu optimalen_US
dc.subjectanalisa jaringan (pert)en_US
dc.subjectpipa distribusi gas bumien_US
dc.subjectoptimal time calculationen_US
dc.subjectnetwork analysis (pert)en_US
dc.subjectnatural gas distribution pipelineen_US
dc.titlePerhitungan Waktu Optimal dengan Metode Analisa Jaringan (Pert) pada Pemasangan Pipa Distribusi Gas Bumi di Pt. Universal Gloves Industrien_US
dc.title.alternativeCalculation of Optimal Time With Analysis Network Method Calculation of Optimal Time With Analysis Network Method (PERT) with Instalation Distribution Pipe of Earth Gas in PT. Universal Gloves Industri(PERT) with Instalation Distribution Pipe of Earth Gas in PT. Universal Gloves Industrien_US
dc.typeSkripsi Sarjanaen_US
Appears in Collections:SP - Industrial Engineering

Files in This Item:
File Description SizeFormat 
018150004 - Iskandar Zulkarnain B. - Fulltext.pdfCover, Abstract, Chapter I, II, III, IV, VI, Bibliography3.55 MBAdobe PDFView/Open
018150004 - Iskandar Zulkarnain B. - Chapter V.pdf
  Restricted Access
Chapter V1.55 MBAdobe PDFView/Open Request a copy


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.